PV -- Planned Value
AC -- Actual Cost
BAC -- Budget At Completion (sum of all PVs)
Cost
CV -- Cost Variance
CV == EV - AC
CPI -- Cost Performance Index
CPI == EV / AC
Schedule
SV -- Schedule Variance
SV == EV - PV
SPI -- Schedule Performance Index
SPI == EV / PV
Forecast
ETC -- Estimated to Complete
EAC -- Estimated at Completion
| Option | ETC | EAC |
|---|---|---|
| New estimate (re-estimate) | ETC | EAC == AC + ETC |
| Atypical variances (using remaining budget) | ETC == BAC-EV | EAC == AC + (BAC-EV) |
| Typical variances (using CPI) | ETC == (BAC-EV)/CPI | EAC == AC + (BAC-EV)/CPI == BAC/CPI |
| (using CPI and SPI) | EAC == AC + (BAC-EV)/(CPI*SPI) |
VAC -- Variance at Completion
VAC == BAC - EAC
To-Complete Performance Index based on BAC
TCPI(BAC) == (BAC-EV) / (BAC-AC)
To-Complete Performance Index based on EAC
TCPI(EAC) == (BAC-EV) / (EAC-AC)
To-Schedule Performance Index
TSPI = (BAC-EV) / (BAC-PV)
No comments:
Post a Comment